April Showers: Snow is still falling, however a break in the snow and freezing winds has allowed the concrete to be poured. The Techrete panels...
On Sunday 17th March 2013 called 'Kevu Maninagar Che Dhaam?' was held in London
Snow and freezing winds have disrupted the concrete pour for the dome and roof. This was scheduled for completion before the Easter break, but...
Construction progress of London's new temple in Kingsbury
A special sabha designed to engage members of all ages and provide an understanding of Jeevanpran Bapashree's unique and divine status and the...
Lower ground slab and columns completed. Ground floor (temple level) slab completed. Temple columns and walls to first floor 40% completed....