London's New Temple Construction Progress Car Entrance: The car entrance view is shown, from Townsend lane. The power sub station room and multifunction hall areas are shown. The main temple has the majority of the cladding up. The front of the office block is being cut away. The temple looks good from Kingsbury Road. 12 May 2013
London's New Temple Construction Progress Taking form: The front cladding has been put in place on the most part. It now looks like a complete building. It does not however look like a mandir,for that we will have to wait for the carvings to go on. The Multifunction hall is fully blocked up and brickwork will start shortly. 28 Apr 2013
London's New Temple Construction Progress April Showers: Snow is still falling, however a break in the snow and freezing winds has allowed the concrete to be poured. The Techrete panels have started to be installed. Additionally the blockwork on the Multi Function hall has started. 14 Apr 2013
Kevu Maninagar Che Dhaam? Sabha On Sunday 17th March 2013 called Kevu Maninagar Che Dhaam? was held. Shree Swaminarayan Temple Maninagar is not only the global headquarters of our Sanstha, it is the true dwelling of Lord Shree Swaminarayan and home to His supreme eternal throne ? Shree Swaminarayan Gadi. The glory and grandeur of this sacred land is unsurpassed ? from Lord Shree Swaminarayan explicitly selecting this site to be His own, to the miraculous, divine and heartening history of how Jeevanpran Swamibapa established the Temple, to the way it has become the beacon from which the true and unadulterated tenets of the supreme Lord Shree Swaminarayanbapa Swamibapa emanate under the inspirational leadership of Acharya Swamishree. In order to explain and evidence this, a special Assembly was held at Shree Swaminarayan Temple London ? created and delivered by the youth, for the youth. 30 Mar 2013
London's New Temple Construction Progress Snow and freezing winds have disrupted the concrete pour for the dome and roof. This was scheduled for completion before the Easter break, but will now happen after. The dome and roof steel work has been prepared and it's ready to go. 29 Mar 2013
London's New Temple Construction Progress Construction progress of London's new temple in Kingsbury 28 Feb 2013
Jeevanpran Abji Bapashree Sabha in London A special sabha designed to engage members of all ages and provide an understanding of Jeevanpran Bapashree's unique and divine status and the establishment of the Satsang Mahasabha was held in London. 05 Feb 2013
London's New Temple Construction Progress Lower ground slab and columns completed. Ground floor (temple level) slab completed. Temple columns and walls to first floor 40% completed. Multi-function hall pile top reinforcement exposure 40% completed. 02 Jan 2013
London's New Temple Construction Progress Latest update of construction progress 20 Dec 2012
London's New Temple Construction Progress Construction progress of London's new temple in Kingsbury 03 Dec 2012