Construction begins. First day The first steel column to be placed for Chicago Mandir First column being positioned First steel column being bolted down to the foundation
Happy to see the first steel column fixated First steel column supported by the crane Second steel column being positioned Second steel column bolted down to the foundation
Two steel columns are connected Posterior portion of the mandir steel columns erected Cross beams and steel columns linked Closer look at the posterior section of the mandir
Preperation to raise the crossed steel beam for the roof Constructors prepare to secure crossed steel beam for the roof Constructor prepares to be raised to the roof of the mandir Crossed steel beam for the roof is raised and positioned
Adjacent crossed steel beams for the roof are fixated First floor and storage floor steel work is placed Longest and heaviest steel beam is connected at the center of column line 3
Closer look at first floor and storage floor steel work Another roof steel beam is lifted for fixation Another roof steel beam is lifted for fixation Forth column line is reached
Work in progress Roof steel fixtures are placed Third column line is complete.JPG Supporting beams for the placement of Shikhar
Supporting beams for the placement of Shikhar Three Shikars beams are supported between column line 3 and 4 Constructors continue with building work Steel columns line 4 completed

   